Don't ask Trans Mountain's owner-operator for a cost estimate or timeline

#246 of 298 articles from the Special Report: Trans Mountain
Trans Mountain workers on the pipeline Anchor Loop Project in Alberta. Photo courtesy of Kinder Morgan Canada

Support strong Canadian climate journalism for 2025

Help us raise $150,000 by December 31. Can we count on your support?
Goal: $150k
$32k

The corporation in charge of the Trans Mountain pipeline expansion project can’t say for certain its construction schedule or how much the project will cost overall.

And it has admitted that recently secured financing is only enough to cover the next few months.

Canada Development Investment Corporation (CDEV), the Crown corporation that owns and operates the pipeline and is overseeing the expansion project, revealed these details during its annual public meeting on Dec. 11, as well as in a recent financial report.

The details make clear that, despite being owned by the government of Canada and promoted by Prime Minister Justin Trudeau as being in the national interest, CDEV and its corporate entities still harbour a significant degree of uncertainty about the project’s timeline and long-term financing.

For years, the expansion project has faced questions over when it will be completed, how much it will ultimately cost and how much of that expense can be passed on to shippers via tolls.

“We’ll need more clarity on the project’s schedule before we can determine the costs,” CDEV chairman Steve Swaffield said at the annual meeting held at the Shaw Centre in Ottawa.

“A revised toll will be made public closer to the in-service date.”

Meanwhile, in a recent financial report, CDEV admitted that “financial commitments have not been obtained to finance the entire project.”

The corporation negotiated a revised credit agreement with a federal fund called the Canada Account on July 30. The loan, or “credit facility,” has a limit of $2.6 billion through the end of 2019 that will increase to $4 billion in 2020 and will mature August 2023.

But this money “should be suitable to fund construction costs for (the Trans Mountain pipeline expansion) through the first half of 2020,” the report says, after which CDEV expects to negotiate again.

“It is imperative that continued and increasing financing sources are obtained in a timely manner,” the corporation wrote. The uncertainty, it said, is leading to “continued financial and completion risk for the project.”

Noreen Flaherty, corporate secretary at CDEV, confirmed to National Observer that the credit agreement was meant to fund pipeline expansion activities “in 2020.”

“CDEV does not expect that agreement to be of a sufficient size” to finance the construction of the entire expansion project, Flaherty said.

The former owner, Kinder Morgan, originally said the construction cost was $7.4 billion, but later filed documents showing it could cost between $8.4 billion and $9.3 billion. Economist Robyn Allan has estimated the current cost has reached $12 billion.

The construction completion date has been variously cited as between 2020 and 2023, depending on how legal and other issues play out.

At the annual meeting, CDEV said work at the Burnaby and Westridge terminals had started in August, pipe is on the ground in Alberta and expected to be “in the ground by Christmas” and the company was “looking forward to being underway with construction in every (section) by next fall.”

A ‘real thing’ or a ‘multibillion-dollar subsidy’?

The expansion project will roughly triple the capacity of the existing Trans Mountain pipeline, sending up to 890,000 barrels a day of crude oil and other petroleum products from the Edmonton area to a terminal in metro Vancouver.

Advocates including the federal government say the expansion project will create jobs and open Canadian fossil fuel products to new markets, generating new economic prosperity.

“We know that no matter how much people talk about information technology or cloud-based whatever, Canadian prosperity has and will continue to be driven by those who know how to build things,” Natural Resources Minister Seamus O’Regan said at a gathering of politicians in a field near Edmonton last week to celebrate construction commencing along the pipeline route.

“Real things, tangible things, things built by people, helping, in this instance, to move our resources from Alberta to new markets where they are needed.”

But critics say the expansion will put Canada’s carbon-pollution-reduction goals out of reach, and comes at the worst time, as the country struggles to deal with an advancing climate crisis.

The oil and gas sector is proportionally the largest polluter by sector countrywide, and Canada's 173 billion barrels of reserves is the third-largest in the world.

The Federal Court of Appeal quashed the government’s original approval in the summer of 2018, saying it had failed in its legal duty to properly consult with First Nations and had carried out an insufficient environmental review.

The Liberal government approved the pipeline project for a second time last June, saying it had fixed both issues. But the court agreed in September that six of 12 fresh challenges could proceed, related to the Crown’s duty to consult and accommodate, and the Crown’s conflict of interest.

The Court of Appeal is now scheduled to hear fresh legal challenges this month from Coldwater Indian Band, Squamish Nation, Tsleil-Waututh Nation and others.

“The Trans Mountain pipeline is already a massive multibillion-dollar subsidy and Canadians have the right to know how much the price has increased,” said Eugene Kung, staff lawyer at West Coast Environmental Law, in a Dec. 10 statement.

“Canadians were told this would be a profit-generating investment and the profits would be devoted to renewable energy. Instead, it’s operating at a consistent loss and it isn’t even clear the government will be able to sell it, without taking another loss of billions of taxpayer dollars.”

‘The existing pipeline remains full’

At the annual meeting, Trans Mountain Corporation chairman William Downe said there had been “significant progress” on the expansion project, and argued the current pipeline’s full capacity demonstrated that there was a case to be made for the expansion.

“The existing pipeline remains full each and every month, with demand from customers exceeding the capacity consistently for the past decade. This demand for space is evidence of the strong and clear business case supporting Trans Mountain expansion,” he said.

“Shippers have made long-term contract commitments ranging from 15-20 years that will underpin the cost of construction and the operation of the pipeline. The additional capacity offered by the expansion will be used to supply more crude oil and refined products to markets in British Columbia and Washington state, and to offshore markets in the Asia-Pacific.”

President Ian Anderson said Trans Mountain has secured 15- and 20-year contracts with 13 shippers in Western Canada that cover 80 per cent of the capacity of the expansion project.

“So we’re fully expanded at 890,000 barrels a day, 80 per cent of that capacity is fully contracted for 20 years. The remaining 20 per cent is available to shippers to access on a month-to-month basis,” he said.

“Long-term financial security for the asset is very well-established with those long-term contracts, and the tolling mechanisms within them.”

The new loan was handled by Export Development Canada (EDC), another Crown corporation that provides support for Canadian exports. Canada Account transactions are administered by EDC, but taxpayers ultimately assume the risk; they are deemed by cabinet to be in Canada’s interest.

Andrew Stafl, vice president of finance at CDEV, confirmed the third-quarter statement from the corporation corresponds to the Canada Account loan agreement, and replaces an earlier one signed on Aug. 29, 2018.

Stafl also confirmed that another transaction, a loan guarantee that the pipeline had with Royal Bank of Canada and TD Bank, was no longer active.